Queensland Korean War Memorial

2nd of June 2011. Day two, start of foundation and concreting.  ( 7cubic mtre. of Concrete )

3rd of June 2011. Day three, wall gets built.  ( Four and a half hours to build. Steel rods between each layer of blocks - holes to be filled with concrete. )

13th June. Day 13. Area Cleaned up. Timber templates for Murals attached to wall.